Our Challenge
The earlier stages of this project were supplied by another provider and there were many issues with poor connections and substandard detailing. This caused significant delays in the erection of the first, smaller structure. Techlam was involved to remedy existing work and progress the next phase of the build.
The Techlam solution
Working with the project managers, we identified the main issues and together decided that the best course of action would be to pre-assemble the entire structure in our plant before dis-assembling it and packing for delivery. This enabled all knife plates and hardware to be checked and tested for correct fit before being delivered to site.